OFFICE OF THE PRESIDENT |
|
 |
|
|
|
THE GENERAL MANAGER |
|
 |
|
J.R. Nereus Acosta, PhD
Secretary/Presidential Adviser
for Environmental Protection |
|
|
|
LLDA MANDATE |
|
The Laguna
Lake Development Authority was established in 1966 as a
quasi-government agency that leads, promotes, and
accelerates sustainable development in the Laguna de Bay
Region. Regulatory and law-enforcement functions are carried
out with provisions on environmental management,
particularly on water quality monitoring, conservation of
natural resources, and community-based natural resource
management.
|
|
|
|
|
|
SHORELAND DEVELOPMENT CLEARANCE |
|
|
|
SCHEDULE OF AVAILABILITY
OF SERVICE:
Monday to Friday, 8:00 am to
5:00 pm
WHO MAY AVAIL OF THE SERVICE:
Local Government Units located within the Laguna de Bay Region.
WHAT ARE
THE REQUIREMENTS:
-
Application form, duly accomplished and signed
- Time table and corresponding budget appropriations
- Engineering and technical plans
- Solid and liquid waste management plans
- Certification from the Municipal Assessors Office that no person is paying the tax of the area
- Certification from the Office of the Municipal Planning Development Officer that there is no other feasible site for the project
- Resolution from the Sanguniang Bayan endorsing the proposed project
- Technical survey plan
Fees
|
Processing Fee |
P 1,600.00 |
|
Lease Fee
: |
Based on the size of the area and zonal value of the area to be utilized using the following formula: |
Clearance fee (with structure)
= area in sq. m. x 5% of zonal value |
Clearance fee (without structure)
= area in sq. m. x 1% of zonal
value |
How to Avail the Service
|
CLIENT |
AGENCY |
|
Step |
Activity |
Activity |
Responsible |
Duration |
1 |
Secures, fills-up, and
submits application form and supporting documents
|
Provides forms, checklist of requirements, and schedule of fees (Includes explanation of requirements and process). |
CPD / Licensing Officer |
20 minutes |
| |
|
Assesses and approves processing and clearance fees (includes the review and evaluation of data that will be used in the computation of fees and recording in the ledger) |
Finance / Accountant
|
20 minutes
|
2 |
Pays processing and clearance fees |
Receives payment and issues Official Receipt (Includes checking of bills to determine genuineness, encoding of official receipt number, date, and amount paid). |
Finance / Cashier |
10 minutes |
| |
|
Receives application and issues claim stub |
CPD / Licensing Officer |
5 minutes
|
| |
|
Evaluates technical documents, conducts site inspection, and prepares evaluation report.
|
CPD / Engineer |
1 day |
| |
|
Reviews and approves evaluation report (includes the review of the evaluation report and determination of extent of complete staff work given to the evaluation of the submitted documents) |
CPD / Head |
1 hour |
| |
|
Prepares Clearance to Develop Shoreland Areas |
CPD / Engineer |
10 minutes |
| |
|
Reviews and recommends approval of Clearance
|
CPD / Head |
20 minutes
|
| |
|
Approves Clearance and affixes LLDA dry seal. (Includes the review of the evaluation report and determination of extent of complete staff work given to the evaluation of the submitted documents)
|
OGM / GM |
4 hours |
3 |
Receives Clearance |
Releases Clearance |
OGM / Clerk |
10 minutes |
- END OF
TRANSACTION - |
|
|
|
|
|
|