DISCHARGE PERMIT RENEWAL

Print

Discharge Permit Application Form Self-Monitoring Report Form Approved DP Application Form

SCHEDULE OF AVAILABILITY OF SERVICE:
Monday to Friday, 8:00 am to 5:00 pm

MUST READ:

MEMORANDUM CIRCULAR NO. 2014-08
Policy and Procedural Guidelines for the Request and Conduct of Resampling and Other Purposes

MEMORANDUM CIRCULAR NO. 2014-09
Policy Guidelines for the Application of Temporary Acceptable Range

MEMORANDUM CIRCULAR NO. 2015-01 (AMENDING MEMORANDUM CIRCULAR No. 2014-03)
“Defining Refusal of Entry and Providing Sanctions Therefor”, Specifically Providing For Higher and Stricter Penalties for Violation Thereof


WHO MAY AVAIL OF THE SERVICE:
Persons, natural or juridical, who are discharging liquid waste into the Laguna de Bay Region.

WHAT ARE THE REQUIREMENTS:
Application form, duly accomplished, signed, and notarized

FEES

  Amount
Processing Fee 5,000.00
 
Fixed Fee (depending on volume of wastewater)
Small Scale 8,000.00
Medium Scale 16,000.00
Large Scale 24,000.00
 

Variable Fee(for BOD and TSS)

Within the standard 5.00/kg BOD/TSS
More than standard 30.00/kg BOD/TSS


HOW TO AVAIL THE SERVICE

CLIENT

AGENCY

Step

Activity

Activity

Responsible

Duration

1

Secures, fills-up, and submits application form and requirements

Provides forms, checklist of requirements, and schedule of fees. (Includes explanation of requirements and process)

CPD / Licensing Officer

20 minutes

   

Assesses and approves fees. (Includes the review and evaluation of data that will be used in the computation of fees and recording in the ledger)

Finance / Accountant

20 minutes

2

Pays fees

Receives payment and issues Official Receipt (Includes checking of bills to determine genuineness, encoding of official receipt number, date, and amount paid).

Finance / Cashier

10 minutes

   

Receives application and issues claim stub

CPD / Licensing Officer

5 minutes

   

Evaluates technical documents and prepares evaluation report. (Includes review of compliance with DP conditions)

CPD / Engineer

12 WD

   

Reviews and approves evaluation report and prepares DP (Includes the review of the evaluation report and determination of extent of complete staff work given to the evaluation of the submitted documents).

CPD / Head

1 hour

   

Approves DP and affixes LLDA dry seal. (Includes the review of the evaluation report and determination of extent of complete staff work given to the evaluation of the submitted documents)

OGM / GM

4 hours

3

Receives DP

Releases DP.

OGM / Clerk

10 minutes

- END OF TRANSACTION -

Notes:

  1. Process includes on-site inspection, collection and analysis of samples.
  2. Rule 14.4 of IRR of RA 9275, “Philippine Clean Water Act of 2004” states that the application shall be acted upon within 30 working days.
  3. The foregoing process applies to application without pending water pollution case.