I. Kalayaan, Laguna Integrated Solid Waste Management Sub-Project II. Liliw, Laguna Community Based Solid Waste Managemen Sub-Project III. Morong Material Recovery Facility with Composting Solid Waste Management Sub-Project IV. Siniloan, Laguna Environmental Enhancement Sub-Project V. Teresa Material Recovery Facility with Composting Solid Waste Management Sub-Project
I. Kalayaan, Laguna Integrated Solid Waste Management Sub-ProjectEstablishment
of an integrated solid waste management system anchored on the
development and operation of a Category-I Disposal Facility, and
construction of access road complemented by a central MRF and
portable waste bins 1. “The Government of the Philippines (GOP) has received a Loan from the World Bank toward the cost of Laguna de bay Institutional Strengthening and Community Participation project (LISCOP), and it intends to apply part or the whole of the proceeds of this loan, together with the GOP counterparts funds, to payments under the contract for the Construction of Kalayaan Integrated Solid Waste management Sub-Project”. 2. The Kalayaan LGU now invites sealed Bids from eligible Bidders for the construction of the Kalayaan Sub-Project including, but not limited to, the construction Category-1 Disposal Facility, access road, composting facility, concrete vault, guard house, central MRF building, gate fence, waste bins, leachate pond, administration building and elevated water tank. Completion of the Works is estimated to finish in 180 calendar days. 3. Bidding will be conducted through open competitive bidding procedures as specified in the Implementing Rules and Regulations (IRR) of Republic Act No. 9184 (R.A. 9184), otherwise known as the Government Procurement Reform Act. Subject to exceptions stated in this Bidding Documents, only Bids from Bidders who pass an eligibility check will be opened. The Bidder with lowest Calculated Bid (LCB) shall advance to the post-qualification stage in order to finally determine its responsiveness to the technical and financial requirements of the project. The contract shall then be awarded to the Lowest Calculated Responsive Bidder (LCRB) who was determined as such during post-qualification. The Estimated Project Cost (EPC) is PHP 14,989,000.00.
4. A complete set of Bidding Documents in English may be purchased by interested Bidders from the address below and upon payment of a nonrefundable fee of P3000.00. The Bidding Documents shall be received personally by the bidder or his authorized representative from February 22 to March 27, 2007.
5. The Kalayaan LGU will hold a Pre-Bid Conference open to all Eligible Bidders on March 12, 2007 at the Municipal Hall of Kalayaan, Laguna, at 10:00 a.m.
6. Eligible Bidders must submit their Bids at the address below on or before March 27, 2007 at 10:00 a.m. All Bids must be accompanied by a Bid security in the form of Bank Guarantee equivalent to P 225,000.00 or in cash, certified / cashiers check, bank draft or irrevocable letter of credit amounting to P 150,000.00. Late Bids shall not be accepted. Bid opening shall be on March 26, 2007, 10:00 AM at the Conference Room, Kalayaan Municipal Hall. Bids will be opened in the presence of the Bidders’ representatives who choose to attend at the address below at 10:00 AM on March 26, 2007.
7. Completion of the Works is required by November 16, 2007 or for a duration of 180 calendar days. 8. The Kalayaan LGU reserves the right to accept or reject any Bid, to annul the bidding process, and to reject all Bids at any time prior to contract award, without thereby incurring any liability to the affected Bidder or Bidders. Engr.
Ruel R. Ragas Municipal
Government of Kalayaan Laguna 4015
Real St., San Juan, Kalayaan, Laguna 049-820-0369 049-5570122
(telefax)
II.Liliw Community Based Solid Waste Managemen Sub-Project 1. “The Government of the Philippines (GOP) has received a Loan from the World Bank toward the cost of Laguna de Bay Institutional Strengthening and Community Participation Project (LISCOP), and it intends to apply part or the whole of the proceeds of this loan, together with the GOP counterpart funds, to payments under the contract for the Construction of Liliw Community-Based Solid Waste Management Sub-Project”. 2. The Liliw LGU now invites sealed Bids from eligible Bidders for the construction of the Liliw Material Recovery Facility with Composting. Completion of the Works is estimated to finish in 180 calendar days. 3. Bidding will be conducted through open competitive bidding procedures as specified in the Implementing Rules and Regulations (IRR) of Republic Act No. 9184 (R.A. 9184), otherwise known as the Government Procurement Reform Act. Subject to exceptions stated in this Bidding Documents, only Bids from Bidders who pass an eligibility check will be opened. The Bidder with lowest Calculated Bid (LCB) shall advance to the post-qualification stage in order to finally determine its responsiveness to the technical and financial requirements of the project. The contract shall then be awarded to the Lowest Calculated Responsive Bidder (LCRB) who was determined as such during post-qualification. The Estimated Project Cost (EPC) is PHP 1, 115,818.03.
4. A complete set of Bidding Documents in English may be purchased by interested Bidders from the address below and upon payment of a nonrefundable fee of 1500.00. The Bidding Documents shall be received personally by the bidder or his authorized representative from February 26 to March 26, 2007.
5. The Liliw LGU will hold a Pre-Bid Conference open to all Eligible Bidders on March 13, 2007 at the Municipal Hall of Liliw, Laguna, at 10:00 a.m.
6. Eligible Bidders must submit their Bids at the address below on or before March 27, 2007 at 10:00 a.m. All Bids must be accompanied by a Bid security in the form of Bank Guarantee equivalent to P 16,740.00 or in cash, certified / cashiers check, bank draft or irrevocable letter of credit amounting to P 11,160.00. Late Bids shall not be accepted. Bid opening shall be on March 27, 2007, 10:00 AM at the Conference Room, Liliw Municipal Hall. Bids will be opened in the presence of the Bidders’ representatives who choose to attend at the address below at 10:00 AM on March 27, 2007.
7. Completion of the Works is required by November 15, 2007 or for a duration of 180 calendar days.
8. The Liliw LGU reserves the right to accept or reject any Bid, to annul the bidding process, and to reject all Bids at any time prior to contract award, without thereby incurring any liability to the affected Bidder or Bidders. Mr.
Antonio D. Ardieta
Municipal Government of Liliw Laguna
Mobile no. 0915-785-7250
Tel no. (049) 563-1001 / 1003
III. Morong Material Recovery Facility with Composting Solid Waste Management Sub-Project 1. “The Government of the Philippines (GOP) has received a Loan from the World Bank toward the cost of Laguna de Bay Institutional Strengthening and Community Participation Project (LISCOP), and it intends to apply part or the whole of the proceeds of this loan, together with the GOP counterpart funds, to payments under the contract for the Construction of Morong Material Recovery Facility with composting Sub-Project”. 2. The Morong LGU now invites sealed Bids from eligible Bidders for the construction of the Morong Material Recovery Facility with Composting. Completion of the Works is estimated to finish in 120 calendar days. 3. Bidding will be conducted through open competitive bidding procedures as specified in the Implementing Rules and Regulations (IRR) of Republic Act No. 9184 (R.A. 9184), otherwise known as the Government Procurement Reform Act. Subject to exceptions stated in this Bidding Documents, only Bids from Bidders who pass an eligibility check will be opened. The Bidder with lowest Calculated Bid (LCB) shall advance to the post-qualification stage in order to finally determine its responsiveness to the technical and financial requirements of the project. The contract shall then be awarded to the Lowest Calculated Responsive Bidder (LCRB) who was determined as such during post-qualification. The Estimated Project Cost (EPC) is PHP 8, 187,658.13
4. A complete set of Bidding Documents in English may be purchased by interested Bidders from the address below and upon payment of a nonrefundable fee of P3,000.00. The Bidding Documents shall be received personally by the bidder or his authorized representative from February 26 to March 26, 2007.
5. The Morong LGU will hold a Pre-Bid Conference open to all Eligible Bidders on March 14, 2007 at the Municipal Hall of Morong, Rizal, at 9:00 a.m.
6. Eligible Bidders must submit their Bids at the address below on or before March 28, 2007 at 9:00 a.m. All Bids must be accompanied by a Bid security in the form of Bank Guarantee equivalent to P 123,000.00 or in cash, certified / cashiers check, bank draft or irrevocable letter of credit amounting to P 81,900.00. Late Bids shall not be accepted. Bid opening shall be on March 28, 2007, 9:00 AM at the Conference Room, Morong Municipal Hall. Bids will be opened in the presence of the Bidders’ representatives who choose to attend at the address below at 9:00 AM on March 28, 2007.
7. Completion of the Works is required by September 7, 2007 or for a duration of 120 calendar days.
8.
The Morong LGU reserves the right to accept or reject any Bid, to
annul the bidding process, and to reject all Bids at any time prior
to contract award, without thereby incurring any liability to the
affected Bidder or Bidders. Engr.
Bayani G. Sunga Municipal
Government of Morong, Rizal Municipal
Bldg. Tupas
St., Brgy. San Pedro Morong,
Rizal Tel
no. (632) 691-6243 Fax
no. (632) 691-6912 Email
Add: baysunga@yahoo.com
IV. Siniloan, Laguna Environmental Enhancement Sub-Project 1. “The Government of the Philippines (GOP) has received a Loan from the World Bank toward the cost of Laguna de Bay Institutional Strengthening and Community Participation Project (LISCOP), and it intends to apply part or the whole of the proceeds of this loan, together with the GOP counterpart funds, to payments under the contract for the Siniloan Environmental Enhancement Sub-Project.” 2. The Siniloan LGU now invites sealed Bids from eligible Bidders for the construction of the Siniloan Community – based solid waste management module and the development of Buruisan Falls and Eco - trail. Completion of the Works is estimated to finish in 120 calendar days. 3. Bidding will be conducted through open competitive bidding procedures as specified in the Implementing Rules and Regulations (IRR) of Republic Act No. 9184 (R.A. 9184), otherwise known as the Government Procurement Reform Act. Subject to exceptions stated in this Bidding Documents, only Bids from Bidders who pass an eligibility check will be opened. The Bidder with lowest Calculated Bid (LCB) shall advance to the post-qualification stage in order to finally determine its responsiveness to the technical and financial requirements of the project. The contract shall then be awarded to the Lowest Calculated Responsive Bidder (LCRB) who was determined as such during post-qualification. The Estimated Project Cost (EPC) is PHP 2, 183,696.66.
4. A complete set of Bidding Documents in English may be purchased by interested Bidders from the address below and upon payment of a nonrefundable fee of P3,000.00. The Bidding Documents shall be received personally by the bidder or his authorized representative from February 26 to March 26, 2007.
5. The Siniloan LGU will hold a Pre-Bid Conference open to all Eligible Bidders on March 12, 2007 at the Municipal Hall of Siniloan, Laguna, at 10:00 a.m.
6. Eligible Bidders must submit their Bids at the address below on or before March 27, 2007 at 10:00 a.m. All Bids must be accompanied by a Bid security in the form of Bank Guarantee equivalent to P 32,800.00 or in cash, certified / cashiers check, bank draft or irrevocable letter of credit amounting to P 21,900.00. Late Bids shall not be accepted. Bid opening shall be on March 27, 2007, 10:00 AM at the Conference Room, Siniloan Municipal Hall. Bids will be opened in the presence of the Bidders’ representatives who choose to attend at the address below at 10:00 AM on March 27, 2007.
7. Completion of the Works is required by September 16, 2007 or for a duration of 130 calendar days.
8.
The Siniloan LGU reserves the right to accept or reject any Bid, to
annul the bidding process, and to reject all Bids at any time prior
to contract award, without thereby incurring any liability to the
affected Bidder or Bidders. Mr.
Gregorio B. Valdenaro Municipal
Administrator E.
Castro St., Brgy. Bagong Brgy., Siniloan,
Laguna Tel No. (044) 813-0202
V. Teresa, Rizal Material Recovery Facility with Composting Solid Waste Management Sub-Project 1. “The Government of the Philippines (GOP) has received a Loan from the World Bank toward the cost of Laguna de Bay Institutional Strengthening and Community Participation Project (LISCOP), and it intends to apply part or the whole of the proceeds of this loan, together with the GOP counterpart funds, to payments under the contract for the Teresa Material Recovery Facility with composting Sub-Project”. 2. The Teresa LGU now invites sealed Bids from eligible Bidders for the construction of the Teresa Material Recovery Facility with Composting. Completion of the Works is estimated to finish in 120 calendar days. 3. Bidding will be conducted through open competitive bidding procedures as specified in the Implementing Rules and Regulations (IRR) of Republic Act No. 9184 (R.A. 9184), otherwise known as the Government Procurement Reform Act. Subject to exceptions stated in this Bidding Documents, only Bids from Bidders who pass an eligibility check will be opened. The Bidder with lowest Calculated Bid (LCB) shall advance to the post-qualification stage in order to finally determine its responsiveness to the technical and financial requirements of the project. The contract shall then be awarded to the Lowest Calculated Responsive Bidder (LCRB) who was determined as such during post-qualification. The Estimated Project Cost (EPC) is PHP 3, 457,438.80
4. A complete set of Bidding Documents in English may be purchased by interested Bidders from the address below and upon payment of a nonrefundable fee of P3,000.00. The Bidding Documents shall be received personally by the bidder or his authorized representative from February 26 to March 26, 2007.
5. The Teresa LGU will hold a Pre-Bid Conference open to all Eligible Bidders on March 14, 2007 at the Municipal Hall of Teresa, Rizal, at 1:00 p.m.
6. Eligible Bidders must submit their Bids at the address below on or before March 28, 2007 at 1:00 p.m. All Bids must be accompanied by a Bid security in the form of Bank Guarantee equivalent to P 51,900.00 or in cash, certified / cashiers check, bank draft or irrevocable letter of credit amounting to P 34,600.00. Late Bids shall not be accepted. Bid opening shall be on March 28, 2007, 1:00 PM at the Conference Room, Teresa Municipal Hall. Bids will be opened in the presence of the Bidders’ representatives who choose to attend at the address below at 1:00 PM on March 28, 2007.
7. Completion of the Works is required by September 7, 2007 or for a duration of 120 calendar days.
8.
The Teresa LGU reserves the right
to accept or reject any Bid, to annul the bidding process, and to
reject all Bids at any time prior to contract award, without thereby
incurring any liability to the affected Bidder or Bidders. Mr.
Policarpio Santiago Municipal
Government of Teresa, Rizal Mobile
No. 0906-372-1444
|
|
|
|
|
All design photos/graphics remain the copyright of Laguna Lake Development Authority No. 70 Asiapro Bldg., San Rafael St., Brgy. Kapitolyo, Pasig City. Tel. Nos. 637-9038; 638-5306; 638-5307; 631-4157 E-mail us at: llda@denr.gov.ph We would like to hear from you. Send your comments and/or suggestions to the Webmaster. |
|